cent on the previous year and we expect volumes to increase in the future.
Around 3,000 people worked over 800,000 hours to finish the project, which was completed ahead of schedule and under budget.
Fonterra Managing Director Global Operations Robert Spurway said the commissioning of the plant was one of the Co-operatives smoothest and most efficient.
The team produced some of the best commissioning figures weve ever seen and the plant has been operating well above budgeted performance.