hile directly in front and behind the space available for the new line the two neighbouring lines were positioned.
The time schedule turned out to be similarly constrained. Since the other production lines handle tubs and cartons, there was no option for temporarily relocating glass filling to another line. Which meant: dismantling of the old and installation of the new line had to be accomplished on the fly. A weeks lost production, that was the maximum we could accept, says Andreas Haberstro