date:Jun 27, 2013
current building. Once installed, the structure will be built up around the deodoriser and the roof replaced.
The first phase of preparation work is nearly completed. This includes the removal of redundant hydrogenation equipment and installation of new soap stock tanks. The second phase, due to start soon, will involve installing the necessary steelwork, blending tanks and a new concrete floor to accommodate the deodoriser.
Production will continue in Hull during this process, with the new E5